    Friday, February 12, 2016

    Nerang–Broadbeach Road widening near Bermuda Street

    Early works started this week on Nerang–Broadbeach Road to add a third lane westbound between Rio Vista and Lakeview boulevards in Mermaid Waters.

    Main Roads and Road Safety Minister Mark Bailey visited the site this morning and said the $1.5 million project was part of the $160.7 million Commonwealth Games Roads package to cater for current and expected future traffic volumes on the Gold Coast.

    “The upgrade involves expanding the road by adding a third westbound lane, resurfacing and implementing new linemarking to help improve traffic flows and increase safety on this busy stretch of Nerang–Broadbeach Road,” Mr Bailey said.

    “Access for pedestrians and cyclists will also be improved with a signalised pedestrian crossing installed at the Manapouri Street intersection and extending the existing shared cyclist and pedestrian path on the southern side to Bermuda Street.

    Mr Bailey said Nerang–Broadbeach Road would be used as a core route for the Gold Coast 2018 Commonwealth Games.

    “There are several road infrastructure upgrades to be completed under the $160.7 million package that all will provide long-term benefits to the Gold Coast community,” Mr Bailey said.

    “These roads projects will provide around 480 jobs at a time when jobs and job security are more important than ever.

    “Plans for safety and capacity improvements to the Gooding Drive roundabout on Nerang–Broadbeach Road worth $5.7 are also being finalised as part of the Commonwealth Games roads package.

    “A total of seven direct jobs will be created between both projects along Nerang–Broadbeach Road which is great for local workers in road construction and related industries.

    “A work site has also been established on Southport–Burleigh Road in preparation for construction of an additional north and southbound lane from Fremar Street to Rudd Street in Broadbeach Waters as part of the $104 million upgrade to Southport–Burleigh Road.”

    The roads package is part of $10 billion in infrastructure funding to support 27,000 jobs in the Queensland budget.

    “The Palaszczuk Government is committed to delivering a safe and reliable road network, and getting on with job of building Gold Coast roads for the future,” he said.

    Mr Bailey said with roadworks happening all across the Gold Coast, motorists are being urged to show patience, allow additional travel time and use alternative routes when possible.

    “The bus stop and shelter near Lakeview Boulevard will be relocated further west in mid-March so public transport users should keep an eye out for signage leading up to that change,” he said.

    “Moggill Constructions are carrying out the works which are expected to be completed in the next four months.”

    ENDS

    Media Contacts:     Minister Bailey                  Tim Shipstone          0419 246 157

                                                                           Amy Hunter              0423 651 484

     

    Commonwealth Games Roads Package works update:

    Southport–Burleigh Road Overview

    Works are underway on the $104 million upgrade to Southport–Burleigh Road to create three traffic lanes in each direction from Southport to Broadbeach Waters. To minimise the impacts to the community, the project will be delivered in three separate packages.

    • Southport–Burleigh Road (North Street to Vespa Crescent)
      BMD Constructions were awarded the contract to create an additional north and southbound lane from North Street to Vespa Crescent. Works to widen the two bridges (Benowa Canal Bridge and Korong Channel Bridge) commenced in January.
    • Southport–Burleigh Road (Vespa Crescent to Fremar Street)
      Detailed design is progressing with tenders expected to be called end of April 2016.
    • Southport–Burleigh Road (Fremar Street to Rudd Street)
      Georgiou Group was awarded the contract to create an additional north and southbound lane from Fremar Street to Rudd Street in Broadbeach Waters. Site establishment is now complete. Major works are expected to start soon. 

    Labrador–Carrara Road (Ross Street) and Ashmore Road intersection upgrade

    Works are continuing to install traffic signals for the intersection. Works are being carried out by McIlwain Civil Engineering

    Olsen Avenue to the Southport–Nerang Road

    Extending to six lanes with intersection upgrades

    Nerang–Broadbeach Road (Gooding Drive roundabout)

    AECOM are working through design options with a preferred option to be finalised by end May 2016. When completed the works will boost traffic capacity at the roundabout.

    Smith Street Motorway (Kumbari Avenue)

    A preferred design is currently being finalised in-house with construction on track to start in mid 2016 to improve the intersection.

    Labrador–Carrara Road (Olsen Avenue)

    Parsons Brinckherhoff | WSP are finalising the design, aiming for a mid-2016 construction start.